Checklist for Complete Installation
11 Liebert
®
InteleCool
2
3.0 CHECKLIST FOR COMPLETE INSTALLATION
___ 1. Proper clearance for service access has been maintained.
___ 2. Equipment is level and mounting fasteners are tight.
___ 3. Ducting completed, if required.
___ 4. Line voltage to power wiring matches equipment nameplate.
___ 5. Power wiring connections completed to disconnect switches, including earth ground. Proper
phase rotation has been observed so that scroll compressor will rotate in the correct direction.
___ 6. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 7. Control wiring connections completed to optional controls.
___ 8. All wiring connections are tight.
___ 9. Foreign materials have been removed from in and around all equipment installed (shipping
materials, construction materials, tools, etc.).
___ 10. Fans and blowers rotate freely without unusual noise.
!
WARNING
Risk of electric shock. Can cause injury and death.
Open all local and remote electric power supply disconnect switches and verify with a
voltmeter that power is Off before working within the electrical connection enclosures.
Potentially lethal voltages exist within this equipment during operation. Observe all cautions
and warnings in this manual. Only qualified service and maintenance personnel should work
with this equipment.